Sorry folks... got tied up with visitors...
Ok, some background...
The system comprises 7.6kw of solar panels and 2.4kw of wind turbine... and was installed primarily as a "back to grid" installation...
So the property remains mains power connected, with the solar/wind charging battery banks for failover due to mains power loss...
Power for the AP system was drawn from a sub-board in the studio, both because it was closest to the proposed site, and because the studio was on it's own seperate seldom/lightly used circuit...
With the above in mind, I requested that circuit be tied back to the battery backup solar controller so that the AP system would failover in the event of mains failure...
And that was the work that the solar company had done during the week proceeding... along with an upgrade of the modem/router which would allow remote monitoring and alarms.
I also wanted to be able to tie the greenhouse and fish shed into a remote monitoring system that I'll be installing shortly...
The reason we upgraded the modem/router was principally because it appeared to be under-powered and/or unstable... or so it was thought...
Grant had indicated when he called that morning... that the system had alarmed a "power fail" condition around 19:30... and successful failover to the battery bank....
This was followed by several short returns to mains power... and almost immediate fail back to battery power... followed by a "battery fail" at 20:30...
All consistant with Nicolle's observations... and the reason she relocated to the main house which still had mains power...
When there she noticed several further intermittant power on/offs to the studio... and at the same time... that the modem router was dropping out and/or resetting...
Grant also noticed about 21:00 that he was no longer receiving alarms... and couldn't maintain a connection to the router/battery controller...